Lead with schedule certainty
Owners care about move-in dates. A Gantt chart with critical path called out wins more contracts than a glossy renderings package.
Safety record is a gate, not a tiebreaker
Publish your EMR, DART, and TRIR for the last three years. Anything above 1.0 EMR requires a written corrective action plan in the bid.
The template outline
Technical Approach
- Constructability review findings
- Means & methods narrative
- Sequencing and phasing diagram
Schedule
- Baseline CPM with critical path
- Long-lead procurement plan
- Weather contingency
Safety
- EMR / DART / TRIR trend
- Site-specific safety plan
- Subcontractor pre-qualification process
Pricing
- GMP with open-book assumptions
- Allowances and contingencies
- Self-perform vs sub split
Frequently asked questions
What is the difference between design-build and CMAR?
Design-build is single-source design and construction under one contract. CMAR keeps the architect separate and brings the contractor on early as a preconstruction advisor.
How is a GMP different from a lump sum?
GMP caps cost but allows shared savings if the project comes in under. Lump sum is a fixed price with no transparency into actuals.